Transformer impulse voltageTransformer Impulse Voltage refers to the transient high voltage pulse suddenly applied to the transformer insulation system due to changes in weather conditions, lightning strikes, etc. in the power system. This pulse voltage has very high peak voltage and fast rise time

Transformer Impact Power Transmission
2024-01
What Are Transformer Copper Losses and Iron Losses
VIEW MORE

Among the losses of the transformer, there are mainly two parts: iron loss and copper loss. So, what is the difference between the iron loss and copper loss of the transformer?The iron loss of the transformer is the loss caused by the iron core in the transformer, and the copper loss of the transfor

What Are Transformer Copper Losses and Iron Losses
2024-01
Conditions and Methods for High Voltage Testing of Power Transformers
VIEW MORE

Electricity is an important energy source for production and daily life in modern society. Ensuring its safe and normal operation is one of the most important tasks of the power system. At present, there are still certain drawbacks and problems in the high-voltage testing of power transformers in Ch

Conditions and Methods for High Voltage Testing of Power Transformers
2024-01
Installation and Commissioning of Oil-Immersed Power Transformers
VIEW MORE

1. Performance and uses of power transformers:1. A step-up transformer can be used to increase the terminal voltage of the generator to tens of thousands or hundreds of thousands of volts to reduce the transmission current and reduce the energy loss on the transmission line without increasing the wi

Installation and Commissioning of Oil-Immersed Power Transformers
2024-01
Three Steps for Power Transformer Installation, Commissioning and Acceptance
VIEW MORE

Power transformer installation(1) Equipment and material preparationThe transformer should be equipped with a nameplate. The nameplate should indicate the name of the manufacturer, technical data such as rated capacity, primary and secondary rated capacity, primary and secondary rated voltage, curre

Three Steps for Power Transformer Installation, Commissioning and Acceptance